October 2016-October 2017 (Phase One)
Construction of rafting over the railway lines behind the East Stand and Matthew Harding Stand begins.
Both Stamford Bridge hotels, a range of bars and restaurants and the Stamford Bridge Health Club are demolished.
May 2017
Chelsea play their last game at Stamford Bridge as it stands, leaving for three years to facilitate the rebuild.
June 2017-September 2018 (Phase Two)
The old Stamford Bridge is demolished. Digging down to accommodate the height of the new stadium begins.
July 2018-October 2019 (Phase Three)
Stadium is constructed from scratch
December 2018-July 2020 (Phase Four)
Fitting out of the surrounding area is completed, with a restaurant/café included on-site along with a new club shop and museum.
August 2020
Chelsea return to play at a 60,000-capacity Stamford Bridge for the first time.